项目管理

Project Specifications Working days
Quote & specification: Specification and quotation will be provided based on comprehensive analysis. In 2 days
Acceptance of quote: Sign this document; pay deposit. 10 days cooling off period is allowed. In 15 days
Pre-approval: Permission of grid-connection from distributor. 1 – 30 days
Logistic: Delivery of all components to your site. 1 – 2 days before installation
Installation: Complete all engineering work on site. Solar system is now generating power! 1 – 5 days
Inspection: Implemented by government authorized electrician. 1 day
FIT application & finalization: Excess solar energy now can be converted to your credit. 1 day